  "illustrative": true,
  "article": "/manufacturing/equipment-downtime-customer-delivery/",
  "assumptions": [
    "Minutes after 08:00 on 2026-10-15 Asia/Shanghai; no breaks or transport.",
    "Resources, materials, people and inspection slots are available as stated.",
    "Alternative resource qualification is assumed approved; not a global optimization."
  ],
  "deadline": 240,
  "inspectionMinutes": 60,
  "plans": [
    {
      "id": "PLAN-0",
      "available": 0,
      "setup": 0,
      "process": 120,
      "expectedFinish": 180,
      "expectedDelay": 0
    },
    {
      "id": "PLAN-A",
      "available": 180,
      "setup": 0,
      "process": 120,
      "expectedFinish": 360,
      "expectedDelay": 120
    },
    {
      "id": "PLAN-B",
      "available": 60,
      "setup": 30,
      "process": 150,
      "expectedFinish": 300,
      "expectedDelay": 60
    }
  ],
  "expectedImprovement": 60
}